Detailed Answer
Post-installation acceptance takes about 1-2 hours: 1. wiring verification (30 min); 2. pairing (5 min); 3. functional test (20 min); 4. safety test (e-stop/loss-of-signal, 15 min); 5. interlock test (10 min); 6. operator training briefing (30 min). LDER provides installation guidance; a professional electrician completes it within half a day. Put into service after acceptance passes.
| Wiring | 30 min |
| Testing | 45 min |
| Training | 30 min |
Note:Installation isn't complete until the acceptance sheet is signed.