Detailed Answer
Metallurgical crane remote control emergency stop requirements: 1. Response <100ms (Lideral LD series); 2. Independent hardwired circuit (not dependent on software); 3. Dual E-stop (transmitter + receiver side); 4. Manual reset required after E-stop; 5. Monthly test record. Metallurgy lifting is high-risk; E-stop reliability is the safety baseline.
| Response | <100ms |
| Circuit | Independent hardwired |
| Test | Monthly |
Note:Measure and record metallurgy crane E-stop monthly for archive.