Detailed Answer
Crane control cabinet wiring process: 1. Mount the receiver in the cabinet (antenna outside the cabinet); 2. Connect receiver power (wide voltage AC24~380V); 3. Output relays → intermediate relays → contactor coils; 4. Wire the E-stop output into the main circuit safety chain; 5. Wire limit/loss-of-signal protection; 6. Check each point against the wiring diagram. The LIDEER LD series includes detailed wiring diagrams; XINGJIA provides technical support.
| Power | Wide voltage |
| Output | Relay → contactor |
| Safety | E-stop in main circuit |
Note:After wiring, test no-load first, then under load.